[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1005286":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1005286,736,1,"单选题","下列关于开工条件联合检查确认的说法中，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确认开工条件一般由生产管理部门牵头组织",false,{"key":16,"text":17,"correct":14},"B","“三查四定”中的“四定”是指定任务、定人员、定时间、定措施",{"key":19,"text":20,"correct":14},"C","中间交接后，施工进入收尾阶段",{"key":22,"text":23,"correct":24},"D","中间交接需要在“三查四定”完成问题整改前进行",true,"本题考查的是化工装置开停工安全技术。D.错误。按照中间交接的标准进行“三查四定”并完成问题整改后，就可以进行中间交接。",{"id":6,"name":27,"category":28,"favorite":29},"安全实务-化工安全","建筑工程",0]