[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-997195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},997195,732,1,"单选题","对于一等及二等尾矿库尾矿坝堆积至( )最终设计坝高时，应当对坝体进行一次全面勘察。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1\u002F3以下",false,{"key":16,"text":17,"correct":14},"B","1\u002F3～1\u002F2",{"key":19,"text":20,"correct":21},"C","1\u002F2～2\u002F3",true,{"key":23,"text":24,"correct":14},"D","2\u002F3以上","《矿库安全监督管理规定》第十九条，上游式尾矿坝堆积至二分之一至三分之二最终设计坝高时，应当对坝体进行一次全面勘察，并进行稳定性专项评价。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产专业实务(原案例)","建筑工程",0]