[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-996751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},996751,732,1,"单选题","根据《工业企业设计卫生标准》(GBZ 1)，下列关于生产经营单位除尘净化系统设计和安装要求的说法中，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","输送含尘气体的管道必须水平设置",true,{"key":16,"text":17,"correct":18},"B","输送含尘气体的管道应与地面成适度夹角",false,{"key":20,"text":21,"correct":18},"C","在有爆炸性粉尘及有毒有害气体的除尘净化系统中，应设置检测装置",{"key":23,"text":24,"correct":18},"D","为便于测试，设计中应在除尘净化系统的适当位置设测试孔","输送含尘气体的风管宜垂直或倾斜敷设，倾斜敷设时，与水平面的夹角应>45度。如必须设置水平管道时，管道不应过长，并应在适当位置设置清扫孔，方便清除积尘，防止管道堵塞。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产专业实务(原案例)","建筑工程",0]