[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-138361":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},138361,73,1,"单选题","对于基本建设投资支出项目，宜采取的效益分析方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","“成本—效益”分析法",true,{"key":16,"text":17,"correct":18},"B","最低费用选择法",false,{"key":20,"text":21,"correct":18},"C","“公共劳务”收费法",{"key":23,"text":24,"correct":18},"D","公共定价法","在长期的财政实践中，国际上总结出一系列针对效益形式不同的支出项目的效益分析方法。①对于那些有直接经济效益的支出项目（如基本建设投资支出），采用“成本—效益”分析法；②对于那些只有社会效益，且其产品不能进入市场的支出项目（如国防支出），采用最低费用选择法；③对于那些既有社会效益又有经济效益，但其经济效益难以直接衡量，而其产品可以全部或部分进入市场的支出项目（如交通、教育等支出），则采用“公共劳务”收费法来衡量和提高财政支出的效益。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 财政税收","经济金融",0]