[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-993447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},993447,726,1,"单选题","在应急管理过程中，加大建筑物安全距离、减少危险物品存在量、设置防护墙等措施，属于应急管理（）阶段所做的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预防",true,{"key":16,"text":17,"correct":18},"B","准备",false,{"key":20,"text":21,"correct":18},"C","响应",{"key":23,"text":24,"correct":18},"D","恢复","在假定事故必然发生的前提下，通过预先采取的预防措施，达到降低或减缓事故的影响或后果的严重程度，如加大建筑物的安全距离、工厂选址的安全规划、减少危险物品的存量、设置防护墙以及开展公众教育等。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产管理","建筑工程",0]