[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-993028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},993028,726,1,"单选题","安全预评价是以（ ）作为研究对象",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设项目可行性研究报告",false,{"key":16,"text":17,"correct":18},"B","拟建建设项目",true,{"key":20,"text":21,"correct":14},"C","建设项目的设施",{"key":23,"text":24,"correct":14},"D","建设项目投产后存在的危险、有害因素","",{"id":6,"name":27,"category":28,"favorite":29},"安全生产管理","建筑工程",0]