[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-992740":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},992740,726,1,"单选题","在作业现场既有正在运行的设备，又有施工改造设备、设施的情况下，必须采取保证作业现场安全的隔离措施。该隔离措施的实施单位是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包单位",false,{"key":16,"text":17,"correct":18},"B","发包单位",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","监管部门","]有些施工现场既有正在生产运行的设备，也有施工改造的设备、设施等，保证安全的设备系统的隔离措施应以发包单位为主实施，承包方应做好核实和确认。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产管理","建筑工程",0]