[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-991991":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},991991,724,1,"单选题","根据《尾矿库安全监督管理规定》，尾矿库运行到设计最终标高或者不再进行排尾作业的，应当在（ ）内完成闭库。特殊情况不能按期完成闭库的，应当报经相应的安全生产监督管理部门同意后方可延期，但延长期限不得超过（ ）个月。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一年，3",false,{"key":16,"text":17,"correct":14},"B","二年，6",{"key":19,"text":20,"correct":21},"C","一年，6",true,{"key":23,"text":24,"correct":14},"D","三年，6","本题考查的是《尾矿库安全监督管理规定》。尾矿库运行到设计最终标高或者不再进行排尾作业的，应当在一年内完成闭库。特殊情况不能按期完成闭库的，应当报经相应的安全生产监督管理部门同意后方可延期，但延长期限不得超过6个月。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]