[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-991989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},991989,724,1,"单选题","依据《建设项目安全设施“三同时”监督管理办法》的规定，建设项目需要试运行的，试运行时间应当不少于30日，最长不得超过（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","90日",false,{"key":16,"text":17,"correct":14},"B","120日",{"key":19,"text":20,"correct":21},"C","180日",true,{"key":23,"text":24,"correct":14},"D","210日","本题考查的是建设项目安全设施施工和竣工验收。高危建设项目竣工后，根据规定建设项目需要试运行的，应当在正式投入生产或者使用前进行试运行；试运行时间应当不少于30日，最长不得超过180日，国家有关部门有规定或者特殊要求的行业除外。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]