[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-991848":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},991848,724,1,"单选题","根据《建设项目安全设施“三同时”监督管理暂行办法》，对高危建设项目竣工后做出试运行规定，其试运行的时间应当不少于30日，最长不超过（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","180日",true,{"key":16,"text":17,"correct":18},"B","200日",false,{"key":20,"text":21,"correct":18},"C","250日",{"key":23,"text":24,"correct":18},"D","360日","本题考查的是建设项目安全设施施工和竣工验收。高危建设项目试运行时间应当不少于30日，最长不得超过180日，国家有关部门有规定或者特殊要求的行业除外。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]