[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-991821":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":24},991821,724,1,"单选题","依据《建设项目安全设施“三同时”监督管理办法》规定，高危建设项目竣工后实行试运行，试运行时间应当不少于（ ）日，最长不得超过（ ）日。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30，60",false,{"key":16,"text":17,"correct":14},"B","60，180",{"key":19,"text":20,"correct":21},"C","30，180",true,{"key":23,"text":17,"correct":14},"D","本题考查的是建设项目安全设施施工和竣工验收。《建设项目安全设施“三同时”监督管理办法》规定，根据规定建设项目需要试运行（包括生产、使用，下同）的，应当在正式投入生产或者使用前进行试运行。试运行时间应当不少于30日，最长不得超过180日，国家有关部门有规定或者特殊要求的行业除外。",{"id":6,"name":26,"category":27,"favorite":28},"安全生产法及相关法律知识","建筑工程",0]