[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-991375":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},991375,724,1,"单选题","依据《建设工程安全生产管理条例》的规定，建设单位应当在拆除工程施工15日前，将（）等资料报送建设工程所在地县级以上人民政府建设行政主管部门或者其他有关部门备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位资质等级证明",true,{"key":16,"text":17,"correct":18},"B","拟进入现场使用的起重机械设备(塔式起重机、物料提升机、外用电梯)的型号、数量",false,{"key":20,"text":21,"correct":18},"C","工程项目负责人、安全管理人员和特种作业人员持证上岗情况",{"key":23,"text":24,"correct":18},"D","建设单位安全监督人员和工程监督人员的花名册","建设单随当在拆除工程施工15日前，报送建设工程所在地县级以上人民政府建设行政主管部门或者其他有关部门备案的资料有：①施工单位资质等级证明；②拟拆除建筑物、构筑物及可能危及毗邻建筑的说明；③拆除施工组织方案；④堆放、清除废弃物的措施。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]