[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-991364":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},991364,724,1,"单选题","建设单位是建设工程的投资主体，在建筑活动中居于主导地位。依据《建设工程安全生产管理条例》的规定，下列关于建设单位安全责任的说法，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位可以根据市场需求压缩合同约定的工期",false,{"key":16,"text":17,"correct":14},"B","建设单位应当自开工报告批准之日起10日内，将保证安全施工的措施报送所在地建设行政主管部门或有关部门备案",{"key":19,"text":20,"correct":14},"C","建设单位应当在拆除工程施工10日前，将有关资料报送所在地建设行政主管部门或有关部门备案",{"key":22,"text":23,"correct":24},"D","建设单位应当根据工程需要向施工企业提供施工现场相邻建筑物的相关资料",true,"A项，不得压缩工期。B、C项，应该为15日前。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]