[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-991208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},991208,724,1,"单选题","依据《国务院关于预防煤矿生产安全事故的特别规定》，被责令停产整顿的煤矿，整改结束后要求恢复生产的，应当由县级以上地方人民政府负责煤矿安全监管的部门自收到恢复生产申请之日起，在规定期限内组织验收完毕。验收的期限是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","60日内",true,{"key":16,"text":17,"correct":18},"B","80日内",false,{"key":20,"text":21,"correct":18},"C","90日内",{"key":23,"text":24,"correct":18},"D","120日内","被责令停产整顿的煤矿应当制定整改方案，落实整改措施和安全技术规定；整改结束后要求恢复生产的，应当由县级以上地方人民政府负责煤矿安全生产监督管理的部门自收到恢复生产申请之日起60日内组织验收完毕。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]