[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-990367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},990367,724,1,"单选题","建设单位应当自领取施工许可证之日起三个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以（ ）为限，每次不超过（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","两次，两个月",false,{"key":16,"text":17,"correct":18},"B","两次，三个月",true,{"key":20,"text":21,"correct":14},"C","三次，两个月",{"key":23,"text":24,"correct":14},"D","三次，三个月","本题考查的是建筑法。建设单位应当自领取施工许可证之日起三个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过三个月。",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]