[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-989225":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},989225,724,2,"多选题","(2018年) 2018 年1 月15 日,某建设单位为其工程领取了施工许可证,因未能按期开工,建设单位于2018 年3 月10 日、5 月10 日两次向发证机关报告了工程准备的进展情况,直到2018 年7月1 日开工建设。关于该工程施工许可证的说法,正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该工程施工许可证自行废止",true,{"key":16,"text":17,"correct":18},"B","延期开工未超过6个月,施工许可证继续有效",false,{"key":20,"text":21,"correct":14},"C","应当在2018年4月15日前申请延期",{"key":23,"text":24,"correct":18},"D","不能按时开工,应当在1个月内报告",{"key":26,"text":27,"correct":14},"E","2018年7月1日开工之前,需要重新申领施工许可证","ACE","【施工许可证和开工报告的有效期】",{"id":6,"name":31,"category":32,"favorite":33},"安全生产法及相关法律知识","建筑工程",0]