[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-989224":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},989224,724,2,"多选题","(2016年)关于施工许可制度的和开工报告制度的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实行开工报告批准制度的工程，必须符合国务院的有关规定",true,{"key":16,"text":17,"correct":18},"B","建设单位领取施工许可证后因故不能按期开工的，最多可延期6个月",false,{"key":20,"text":21,"correct":14},"C","建设工程因故中止施工满一年的，恢复施工前应报发证机关核验施工许可证",{"key":23,"text":24,"correct":14},"D","实行开工报告批准制度的工程，因故不能按期开工超过6个月的的工程，应当重新办理开工报告审批手续",{"key":26,"text":27,"correct":18},"E","实行开工报告批准制度的工程，其开工报告主要反映的是施工企业应具备的开工条件","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"安全生产法及相关法律知识","建筑工程",0]