[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-989223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},989223,724,1,"单选题","(2018年)分包工程总承包发生质量问题时,关于总分包质量责任的说法,正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位必须先向总承包单位请求赔偿,不足部分再向分包单位请求赔偿",false,{"key":16,"text":17,"correct":14},"B","建设单位应当在分包合同价款限额内向分包单位求偿",{"key":19,"text":20,"correct":21},"C","其他受害人可以向分包单位请求赔偿,也可以向总承包单位请求赔偿",true,{"key":23,"text":24,"correct":14},"D","其他受害人必须先向分包单位请求赔偿，不足部分再向总承包单位请求赔偿","",{"id":6,"name":27,"category":28,"favorite":29},"安全生产法及相关法律知识","建筑工程",0]