[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988704":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988704,723,2,"多选题","审核计划包括的内容有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","审核目的、审核准则和引用文件",true,{"key":16,"text":17,"correct":14},"B","审核范围，包括确定受审核的组织单元和职能单元及过程",{"key":19,"text":20,"correct":21},"C","记录f目息的表格",false,{"key":23,"text":24,"correct":21},"D","检查表和审核抽样计划",{"key":26,"text":27,"correct":14},"E","现场审核活动的日期和地点","ABE","审核计划是指对一次审核活动和安排的描述。审核计划应包括：①审核目的； ②审核准则和引用文件；③审核范围，包括确定受审核的组织单元和职能单元及过程； ④现场审核活动的日期和地点；⑤现场审核活动预期的时间和期限，包括与受审核方管 理层的会议及审核组会议；⑥审核组成员和陪同人员的作用和职责；⑦为审核的关键区 域配置适当的资源。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]