[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988702":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988702,723,2,"多选题","在质量管理体系审核活动中，审核的启动包括的步骤有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","指定审核组长",true,{"key":16,"text":17,"correct":14},"B","确定审核目的、范围和准则",{"key":19,"text":20,"correct":14},"C","选择审核组",{"key":22,"text":23,"correct":14},"D","与受审核方建立初步联系",{"key":25,"text":26,"correct":27},"E","审核组工作分配",false,"ABCD","审核的启动主要包括五个步骤：①指定审核组长；②确定审核目的、范围和准 贝IJ;③确定审核的可行性；④选择审核组；⑤与受审核方建立初步联系。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]