[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988693":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988693,723,2,"多选题","审核中与受审核方沟通的内容可包括（ ）。[2008年真题]",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","审核计划的修改",true,{"key":16,"text":17,"correct":14},"B","审核证据显示有重大风险",{"key":19,"text":20,"correct":14},"C","审核证据表明不能达到审核目的",{"key":22,"text":23,"correct":24},"D","不合格项纠正措施的描述",false,{"key":26,"text":27,"correct":14},"E","通报审核进展和问题","ABCE","在审核中，适当时，审核组长应定期向受审核方和审核委托方通报审核进展及 相关情况。在审核中收集的证据显示有紧急的和重大的风险时，应及时报告受审核方, 适当时向审核委托方报告。对于超出审核范围之外的引起关注的问题，应指出并向审核 组长报告，可能时，向审核委托方和受审核方通报。当获得的审核证据表明不能达到审 核目的时，审核组长应向审核委托方和受审核方报告理由以确定适当的措施。这些措施 可以包括重新确认或修改审核计划、改变审核目的、审核范围或终止审核。随着现场审 核的进展，若出现需要改变审核范围的任何情况，应经审核委托方和（适当时）受审核 方的评审和批准。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]