[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988692":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988692,723,2,"多选题","质量管理体系审核报告的内容主要有（ ）。[2012年真题]",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","审核目的",true,{"key":16,"text":17,"correct":14},"B","审核准则",{"key":19,"text":20,"correct":14},"C","审核发现",{"key":22,"text":23,"correct":14},"D","审核结论",{"key":25,"text":26,"correct":27},"E","纠正措施的验证情况",false,"ABCD","审核报告应提供完整、准确、简明和清晰的审核记录，并包括或引用以下内容： ①审核目的；②审核范围，尤其是应明确受审核的组织单元和职能单元或过程以及审核 所覆盖的时期；③明确审核委托方；④明确审核组长和成员；⑤现场审核活动实施的日 期和地点；⑥审核准则；⑦审核发现；⑧审核结论。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]