[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988688":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988688,723,2,"多选题","质量管理体系审核的主要活动包括（ ）。[2012年真题]",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","审核的启动",true,{"key":16,"text":17,"correct":14},"B","文件评审的实施",{"key":19,"text":20,"correct":21},"C","不符合纠正措施的验证",false,{"key":23,"text":24,"correct":14},"D","审核报告的编制",{"key":26,"text":27,"correct":21},"E","监督审核","ABD","典型的质量管理体系审核的主要活动包括：①审核的启动；②文件评审；③现场 审核的准备；④现场审核的实施；⑤审核报告的编制、批准和分发；⑥审核的完成。纠 正措施的验证属于质量管理体系认证的主要活动。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]