[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},988571,723,1,"单选题","控制采购过程不包括对（ ）的控制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","评价和选择供方",false,{"key":16,"text":17,"correct":14},"B","规定采购产品的要求",{"key":19,"text":20,"correct":14},"C","采购产品的验证",{"key":22,"text":23,"correct":24},"D","供方生产所需的劳动力",true,"控制采购过程主要包括：①组织应加强对供方的控制，制定选择、评价和重新评 价供方的准则，根据供方按组织的要求提供产品的能力，包括管理能力、过程能力，评 价和选择供方；②为了确保采购的产品符合规定的采购要求，组织提供的采购信息应准 确表述拟采购的产品，规定采购的要求；③为确保采购的产品符合规定的采购要求，组 织应确定并实施所需的检验和其他必要的活动。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业综合知识","建筑工程",0]