[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},988569,723,1,"单选题","设计和开发的更改主要是指对巳经评审、验证或确认的（ ）的更改。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计内容",false,{"key":16,"text":17,"correct":18},"B","设计结果",true,{"key":20,"text":21,"correct":14},"C","设计过程",{"key":23,"text":24,"correct":14},"D","设计要求","设计和开发的更改主要是对巳经评审、验证或确认的设计结果（包括设计和开发 的各阶段）的更改。组织应首先对这种更改加以识别，包括更改的内容和范围，更改的 必要性和可行性，并保持记录。在识别更改的基础上，组织应对设计和开发更改的内容 进行评审、验证和确认，并在更改实施前得到批准。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业综合知识","建筑工程",0]