[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988264":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988264,723,2,"多选题","下列质量成本费用项目中，属于预防成本的有（ ）。[2010年真题]",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","质量培训费",true,{"key":16,"text":17,"correct":14},"B","生产前预评审费用",{"key":19,"text":20,"correct":14},"C","供应商评价费",{"key":22,"text":23,"correct":24},"D","外购材料检验费",false,{"key":26,"text":27,"correct":24},"E","顾客投诉问题处理费","ABC","预防成本的项目包括：①质量策划费用；②过程控制费用；③顾客调查费用； ④质量培训以及提高工作能力的费用；⑤产品设计鉴定费；⑥质量体系的研究和管理费 用；⑦供应商评价费用；⑧其他预防费用。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]