[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},988236,723,1,"单选题","下列属于预防成本的项目是（ ）。[2008年真题]",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量策划费",true,{"key":16,"text":17,"correct":18},"B","质量投诉处理费",false,{"key":20,"text":21,"correct":18},"C","质量审核费",{"key":23,"text":24,"correct":18},"D","试验费","预防成本的项目包括：①质量策划费用；②过程控制费用；③顾客调查费用； ④质量培训以及提高工作能力的费用；⑤产品设计鉴定费；⑥质量体系的研究和管理费 用；⑦供应商评价费用；⑧其他预防费用。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业综合知识","建筑工程",0]