[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988110":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988110,723,2,"多选题","在试制阶段，企业应与供应商在（ ）方面达成一致。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","产品规格",false,{"key":16,"text":17,"correct":18},"B","质量要求",true,{"key":20,"text":21,"correct":18},"C","技术标准",{"key":23,"text":24,"correct":14},"D","产品价格",{"key":26,"text":27,"correct":18},"E","测量系统要求","BCE","在试制阶段，考虑到工作的连续性，企业应有意识地与供应商在质量要求、技术 标准、质量管理体系要求、测量系统要求等方面达成一致，尽量使成批生产时的供应商 从试制阶段的供应商中产生。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]