[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988106":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988106,723,2,"多选题","供应商的质量控制的阶段包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","产品设计和开发阶段的控制",true,{"key":16,"text":17,"correct":14},"B","批量生产阶段的控制",{"key":19,"text":20,"correct":21},"C","试制阶段的控制",false,{"key":23,"text":24,"correct":21},"D","设计和开发策划阶段的控制",{"key":26,"text":27,"correct":21},"E","质量检验的管理","AB","供应商的质量控制阶段有：①产品设计和开发阶段对供应商的质量控制。分为设 计和开发策划阶段对供应商的质量控制、试制阶段对供应商的质量控制。②批量生产阶 段对供应商的质量控制。包括对供应商质量保证能力的监控和质量检验的管理。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]