[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988098":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988098,723,2,"多选题","下列有关供应商审核的说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","审核是针对所有的初选供应商进行的，是对所有列人合格供应商名单中的全部供应 商都要进行政绩考核",true,{"key":16,"text":17,"correct":18},"B","审核时，企业可选派有经验的审核员或委托有资格的第三方审核机构到供应商处进 行现场审核和调査。企业应有自己的审核标准，把握关键过程",false,{"key":20,"text":21,"correct":18},"C","对原有的供应商的审核一般分为例行审核和特殊情况下的审核两种",{"key":23,"text":24,"correct":14},"D","供应商审核一般分为产品审核和质量管理体系审核两类",{"key":26,"text":27,"correct":18},"E","对供应商的审核顺序一般是首先进行产品审核，然后进行过程审核，最后进行质量 管理体系审核","AD","A项，审核不是针对所有的初选供应商进行的，也不是对所有列入合格供应商名 单中的全部供应商都要进行绩效考核，这是因为供应商审核会耗费企业的人力和物力， 必须有针对性地进行。D项，供应商审核一般分产品审核、过程审核和质量管理体系审 核三类。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]