[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988094":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},988094,723,2,"多选题","企业对供应商的情况进行调查发现，此供应商还未获得质量管理体系认证证书，意味着 此供应商（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","未按照ISO 9001标准建立体系",true,{"key":16,"text":17,"correct":18},"B","质量不符合要求",false,{"key":20,"text":21,"correct":18},"C","质量管理体系不健全",{"key":23,"text":24,"correct":18},"D","没有管理体系",{"key":26,"text":27,"correct":14},"E","按照ISO 9001标准建立了质量管理体系，但没有认证","AE","企业未获得质量管理体系认证证书，可能未按照ISO 9001标准建立体系，也可 能按照ISO 9001标准建立了质量管理体系但没有寻求认证，但这并不意味它的质量管理 体系不健全，更不意味着它没有管理体系。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业综合知识","建筑工程",0]