[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-988058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},988058,723,1,"单选题","对未通过体系认证的供应商，企业应着重从控制的有效性人手，关注其（ ）等重要过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采购、设备、人员、检验",true,{"key":16,"text":17,"correct":18},"B","采购、设备、生产、检验",false,{"key":20,"text":21,"correct":18},"C","采购、设备、检验、销售",{"key":23,"text":24,"correct":18},"D","开发、设备、人员、检验","供应商审核时，企业可选派有经验的审核员或委托有资格的第三方审核机构到供应商处进行现场审核和调查。企业应有自己的审核标准，把握关键过程。对未通过体系认证的企业，应着重从控制的有效性入手，关注其采购、设备、人员、检验等重要过程。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业综合知识","建筑工程",0]