[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},987849,722,1,"单选题","某机械厂机加工车间长期从事传动轴的切削加工。最近，为了进一步提高加工质量，车间自发成立了QC小组，在确定课题后，对不同设备和班次的产品进行轴的重量和外後尺寸的波动调查。 为了将对策进度纳入控制，他们可以使用（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","树图",false,{"key":16,"text":17,"correct":14},"B","亲和图",{"key":19,"text":20,"correct":21},"C","网络图",true,{"key":23,"text":24,"correct":14},"D","矩阵图","网络图又称为网络计划技术，它是安排和编制最佳日程计划，有效地实施进度管理的一种科学管理方法，又称为矢线图。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]