[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987803":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},987803,722,2,"多选题","某企业实施质量改进项目，采用网络图法。根据所搜集的资料绘制的网络图如图所示。根据图形可分析出： 网络图中的“虚作业”是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不占时间",true,{"key":16,"text":17,"correct":14},"B","指明先后作业前进方向",{"key":19,"text":20,"correct":14},"C","先后作业有逻辑关系",{"key":22,"text":23,"correct":24},"D","省略作业时间",false,"ABC","网络图中的“虚作业”是指作业时间为零的一种作业，它不占时间，其作业是把先后的作业连接起来。表明先后作业有先后逻辑关系，指明先后作业前进方向。",{"id":6,"name":28,"category":29,"favorite":30},"中级质量专业理论与实务","建筑工程",0]