[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987802":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},987802,722,1,"单选题","某企业实施质量改进项目，采用网络图法。根据所搜集的资料绘制的网络图如图所示。根据图形可分析出： 箭条图中（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","因为有缺口，所以可以有闭环",false,{"key":16,"text":17,"correct":14},"B","可以出现闭环",{"key":19,"text":20,"correct":14},"C","因为两个节点间只能有一项作业，所以应该有闭环",{"key":22,"text":23,"correct":24},"D","不能出现闭环",true,"网络图绘制规则包括：①网络图中每一项作业都应有自己的节点编号，编号从小到大，不能重复；②网络图中不能出现闭环；③相邻两个节点之间，只能有一项作业，只能有一个箭条；④网络图只能有一个起始节点和一个终点节点；⑤网络图绘制时，不能有缺口。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]