[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987800":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},987800,722,1,"单选题","某企业实施质量改进项目，采用网络图法。根据所搜集的资料绘制的网络图如图所示。根据图形可分析出： 图中的关键线路为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①-②-③-④-⑤-⑥",false,{"key":16,"text":17,"correct":18},"B","①-②-③-⑤-⑥",true,{"key":20,"text":21,"correct":14},"C","①-③-⑤-⑥",{"key":23,"text":24,"correct":14},"D","①-④-⑥","作业时间的计算如表所示。 从上表可以看出关键工序为A、D、G、K，因此，关键线路为①-②-③-⑤-⑥。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]