[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},987786,722,1,"单选题","某轴承厂1~4月份的顾客投诉和所有的现场检测记录如下：轴承滚齿不合格40项、外观不合格5项、键槽尺寸不合格2项、外径不合格1项、内径不合格1项、长度不合格1项。质量管理部门针对现有质量问题进行改进，请对下列情况进行分析。 通过召开各阶层部门参与的质量原因分析会，初步推测了影响关键质量问题的主要原因后，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","立即针对主要原因采取措施",false,{"key":16,"text":17,"correct":18},"B","对主要原因进一步验证",true,{"key":20,"text":21,"correct":14},"C","申请配置所需资源",{"key":23,"text":24,"correct":14},"D","针对改进措施进行人员培训","如果只是初步推测了影响关键质量问题的主要原因，不能直接采取对策，说明问题还没有分析到位。要想改进有效果，原因必须要细分，直至能采取措施为止。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]