[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987752":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987752,722,2,"多选题","网络图中的节点（ ），只是一个时间上的“交接点”。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","占用时间",false,{"key":16,"text":17,"correct":18},"B","不占用时间",true,{"key":20,"text":21,"correct":14},"C","消耗资源",{"key":23,"text":24,"correct":18},"D","不消耗资源",{"key":26,"text":27,"correct":14},"E","只消耗资源，不占时间","BD","在网络图中，节点是表示某一项作业的开始或结束，它不消耗资源，也不占用时间，只是时间的一个“交接点”。节点上所标的两个时间为节点最早开工时间和最迟完工时间。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]