[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987751":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987751,722,2,"多选题","甘特图的缺点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","难以给出极详细的计划",true,{"key":16,"text":17,"correct":18},"B","难以判断进度上的非重点",false,{"key":20,"text":21,"correct":14},"C","在计划阶段不便于反复推敲与思考",{"key":23,"text":24,"correct":14},"D","进入实施阶段后的情况变化与计划变更难以处理",{"key":26,"text":27,"correct":14},"E","不能获得有关某项作业迟滞对整个计划影响的正确情报","ACDE","甘特图只能给出比较粗略的计划简单的作业指示，由于表现不出作业间的从属关系，它存在的缺点有：①难以给出极详细的计划；②在计划阶段不便于反复推敲与思考；③进入实施阶段后的情况变化与计划变更难以处理；④不能获得有关某项作业迟滞对整个计划影响的正确情报；⑤设计规模稍大即难以掌握计划全貌；⑥难以判断进度上的重点。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]