[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987750":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987750,722,2,"多选题","在网络图中，计算时间值的目的包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定整个工程的工期",true,{"key":16,"text":17,"correct":18},"B","确定各个分项工程的进度及效率",false,{"key":20,"text":21,"correct":14},"C","确定关键线路，便于控制工程进度",{"key":23,"text":24,"correct":14},"D","计算非关键工序的时差",{"key":26,"text":27,"correct":18},"E","计算关键工序的时差","ACD","计算时间值的目的包括：①确定整个工程的工期；②确定关键线路，便于控制工程进度。关键线路是由关键工序组成的，关键路线上的活动是影响整个工程进度的主要因素；③计算非关键工序的时差。有时差的工序是非关键工序，计算时差的目的在于合理安排和调度劳动力、机器设备、物料和时间等资源。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]