[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987748":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987748,722,2,"多选题","下列关于作业的说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在网络图中，作业活动用箭条—表示",true,{"key":16,"text":17,"correct":18},"B","在网络图中，虚作业占用资源和时间",false,{"key":20,"text":21,"correct":14},"C","在网络图中，作业活动的箭条所指方向为作业前进的方向，箭条图上方的文字表示作业的名称，箭条下方的数字表示作业活动所需的时间",{"key":23,"text":24,"correct":14},"D","在网络图中，虚作业是指作业时间为零的一种作业",{"key":26,"text":27,"correct":14},"E","在网络图中，虚作业不占用时间，其作用是把先后的作业连接起来，表明它们之间的先后逻辑关系，指明作业进行的方向","ACDE","虚作业指作业时间为零的一种作业，以虚箭条一>表示，它不占用时间，其作用是把先后的作业连接起来，表明它们之间的先后逻辑关系，指明作业进行的方向。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]