[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987746":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987746,722,2,"多选题","箭条图是（ ）等方法的结合。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","过程决策程序图法",false,{"key":16,"text":17,"correct":18},"B","计划评审法",true,{"key":20,"text":21,"correct":14},"C","亲和图法",{"key":23,"text":24,"correct":18},"D","关键路线法",{"key":26,"text":27,"correct":14},"E","甘特图","BD","箭条图（网络图）是计划评审法PERT(Program Evaluation Review Technique)和关键路线法CPM( Critical Path Method)两种方法的结合。PERT是20世纪50年代后期，美国海军在制订北极星导弹研制计划时，提出了一种计划管理方法；CPM是1956年美国的杜邦和兰德公司为了协调公司内部不同业务部门的工作而提出的方法。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]