[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987745":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987745,722,2,"多选题","在质量管理中，使用PDPC法有助于（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","在解决问题的过程中，恰当地提出所可能的手段或措施",true,{"key":16,"text":17,"correct":14},"B","在实施过程中碰到问题能迅速采取对策",{"key":19,"text":20,"correct":21},"C","新产品研制过程中质量的展开",false,{"key":23,"text":24,"correct":21},"D","识别存在的质量问题并寻求其解决的办法",{"key":26,"text":27,"correct":21},"E","分清因果关系","AB","在质量管理中，用PDPC法有助于在解决问题过程中，恰当地提出所有可能的手段或措施，在实施过程中碰到困难时，能迅速采取对策，其具体用途包括：①制订方针目标管理中的实施计划；②制订科研项目的实施计划；③在系统或产品设计时，对整个系统的重大事故或故障进行预测；④提前预测制造过程会出现的异常和误操作，制订控制工序的方案和措施。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]