[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987742":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987742,722,2,"多选题","PDPC法是为了完成某个任务或达到某个目标，在（ ）时，预测可能出现的障碍和结果，并相应地提出多种应变计划的一种方法。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","出现质量问题",false,{"key":16,"text":17,"correct":18},"B","制定行动计划",true,{"key":20,"text":21,"correct":18},"C","进行方案设计",{"key":23,"text":24,"correct":14},"D","寻找措施方案",{"key":26,"text":27,"correct":14},"E","进行因果分析","BC","",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]