[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987726":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987726,722,2,"多选题","某部门遇到下列五个需要解决的问题，其中可用排列图解决的问题有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","发现产品不合格项目",false,{"key":16,"text":17,"correct":18},"B","找出造成质量损失的主要方面",true,{"key":20,"text":21,"correct":14},"C","计划变更后的措施",{"key":23,"text":24,"correct":18},"D","质量改进项目的顺序",{"key":26,"text":27,"correct":14},"E","确定某工序的关键路线","BD","质量问题是以质量损失的形式表现出来，找出造成质量损失的主要方面，用排列图可以实现这一目的。排列图采用简单图示技术对项目进行发生频次从最高到最低排列，找出“关键的少数”，从而解决质量改进项目的顺序问题。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]