[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987708":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987708,722,2,"多选题","网络图中关键线路的特征有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","关键线路上工序总时差为0",true,{"key":16,"text":17,"correct":14},"B","关键线路中是起点到终点的耗时最长的路",{"key":19,"text":20,"correct":21},"C","关键线路上工序最早开工时间等于最迟开工时间",false,{"key":23,"text":24,"correct":14},"D","关键线路上工序最早完工时间等于最迟完工时间",{"key":26,"text":27,"correct":21},"E","关键线路上工序作业时间为0","ABD","关键线路是由关键工序组成的。关键工序就是在完成该工序的时间上，没有富裕时间，总时差为零。将关键工序连接起来，就是关键路线。在网络图中，关键路线是所有线路中耗时最长的线路。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]