[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987707":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987707,722,2,"多选题","网络图中节点一般用 表示。关于tE和tL的说法，正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","tE为最早开工时间",true,{"key":16,"text":17,"correct":14},"B","tL为最迟完工时问",{"key":19,"text":20,"correct":21},"C","tE为最早完工时间",false,{"key":23,"text":24,"correct":21},"D","tL最迟开工时间",{"key":26,"text":27,"correct":21},"E","(tE-tL)为最长开工时间","AB","节点是表示某一项作业的开始或结束，在网络图图中用 表示，也称事件。节点不消耗资源，也不占用时间，只是时间的一个“交接点”。其中tE、tL分别表示节点最早开工时间和最迟完工时间。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]