[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987704":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987704,722,2,"多选题","关于PDPC法的说法，正确的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","PDPC法可从全局、整体上掌握系统的状态",true,{"key":16,"text":17,"correct":14},"B","PDPC法可按时间顺序掌握系统的进展情况",{"key":19,"text":20,"correct":14},"C","PDPC法能掌握产生非理想状态的原因",{"key":22,"text":23,"correct":24},"D","PDPC图一经确定不能改变",false,{"key":26,"text":27,"correct":14},"E","PDPC法可补充过去没有想到的措施","ABCE","D项，PDPC图不是一成不变的，要根据具体情况，每隔一段时间修改一次。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]