[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987699":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},987699,722,2,"多选题","对于绘制因果图，下列叙述中正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定“结果”时应结合具体需要，为了避免绘制过多的图，可将不同的“结果”放在一张图中进行分析",false,{"key":16,"text":17,"correct":18},"B","绘制因果图一般有逻辑推理法和发散整理法两种方式",true,{"key":20,"text":21,"correct":18},"C","可以结合头脑风暴法一起使用",{"key":23,"text":24,"correct":18},"D","确定的原因应尽可能具体，应细分到能采取措施为止",{"key":26,"text":27,"correct":14},"E","因果图一旦确定，即不能更改","BCD","A项，有多少质量问题，就要绘制多少张因果图。若许多因素只用一张因果图来分析，势必使因果图大而复杂，无法管理。解决问题也很困难，无法对症下药；E项，因果图使用时要不断加以改进。",{"id":6,"name":31,"category":32,"favorite":33},"中级质量专业理论与实务","建筑工程",0]