[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-987675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},987675,722,1,"单选题","网络图是安排和编制（ ），有效地实施进度管理的一种科学管理方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最快路径",false,{"key":16,"text":17,"correct":18},"B","最佳日程计划",true,{"key":20,"text":21,"correct":14},"C","最好途径",{"key":23,"text":24,"correct":14},"D","快捷方式","网络图又称网络计划技术，它是安排和编制最佳日程计划，有效地实施进度管理的一种科学管理方法。其工具是箭条图，故又称矢线图。",{"id":6,"name":27,"category":28,"favorite":29},"中级质量专业理论与实务","建筑工程",0]